From finished lot to keys

Once a street is paved and the lots are finished, building a home takes most of a year. Here is how that time breaks down for a typical two-story home in the Carolinas.
| Stage | Typical time |
|---|---|
| Permits and plan review | 2–6 weeks |
| Foundation | 2–3 weeks |
| Framing and roof | 3–5 weeks |
| Plumbing, electrical, HVAC rough-in | 3–4 weeks |
| Insulation and drywall | 3 weeks |
| Interior finishes | 6–8 weeks |
| Exterior, driveway, landscaping | Runs alongside interiors |
| Final inspections and certificate of occupancy | 1–2 weeks |
Where time is lost
Inspections are scheduled by the local building department, and a missed inspection can push every following trade back. Weather slows foundations and roofing. Some materials, such as windows and electrical gear, can have long lead times, so we order them before framing starts.
Building many homes at once
On a neighborhood, homes are started in waves so each trade can move from house to house. That keeps crews busy and lets the street fill in steadily.
Before closing
Every home gets a walkthrough before closing, a punch list, and a final cleaning. The warranty starts at closing.